Cedar Lake Road and Louisiana Avenue Improvements
The Cedar Lake Road Improvements project in St. Louis Park is the culmination of several years of planning by the City of St. Louis Park, with federal and state partners helping to secure additional funding. The reconstruction project for Cedar Lake Road this year and Louisiana Avenue next year will bring much needed modernization to the roads and provide equitable opportunities for transportation to underserved populations, improve neighborhood livability and replace existing facilities at the end of their useful life. The city received $2 million in federal infrastructure funds and $5 million in state bonding funds to help cover project costs.
The project consists of three distinct parts that will be constructed separately, as outlined in the map:
- Phase I - 2024 - Cedar Lake Road improvements (Highway 169 to Rhode Island Avenue)
- Phase II - 2025 - Louisiana Avenue improvements (Wayzata Boulevard to Fire Station)
- Phase III - 2026
- Roundabout at the intersection of Cedar Lake Road and Louisiana Avenue
- Louisiana Avenue improvements (Fire Station to BNSF railroad)
- Cedar Lake Road improvements (Rhode Island Avenue to Kentucky Avenue)
Cedar Lake Road and Louisiana Avenue Improvements project will include the following:
- New pavement
- Intersection improvements at Cedar Lake Road and Louisiana Avenue
- Enhancements for people walking and rolling, including curb extensions, raised medians and upgrades to ensure ADA compliance
- Accommodations for people biking
- Streetscape improvements
Latest updates
Nov. 4, 2024
The city will be hosting an open house to view the final plans for the Cedar Lake Road and Louisiana Avenue Improvements project that is scheduled for construction in 2025 and 2026. At this meeting, you will learn what to expect during construction and view layouts showing information on street, sidewalk, bicycle, and utility improvements.
We want to make sure everyone has an opportunity to get this information, so we have provided multiple ways to get involved.
- Attend an in-person open house - Thursday, Dec. 5, 2024, 5:30 - 7:00 p.m.
- Presentation at 6 p.m.
- Westwood Hills Nature Center (Willow and Aspen rooms) - 8300 West Franklin Avenue, St. Louis Park
-
Contact city staff to set up a virtual or in-person meeting to view the layouts and discuss any concerns you may have.
Open house invitation letter - Dec. 5, 2024
Design plans
- Cedar Lake Road approved design
- Louisiana Avenue approved design
Final plans for the Louisiana Avenue and Cedar Lake Road between Rhode Island and Kentucky avenues will be developed in 2024, with construction beginning in 2025.
Latest updates
2024 staging schedule and detour route
Nov. 13, 2024
City contractor, Eureka Construction, is working on the 2024 Cedar Lake Road project.
Traffic impacts
- West, Middle and East Stage- Cedar Lake Road between Jordan Avenue and Rhode Island Avenue– CLOSED TO THROUGH TRAFFIC.
- Please use the posted detour.
- Cedar Lake Road is scheduled to be opened to traffic on Friday, November 22.
School and Church impacts
- Westwood Lutheran Church and School
- Access to Westwood Lutheran Church is through the west stage. Please see the Westwood Church access map.
- Park Spanish Immersion School
- Access to Park Spanish Immersion School will be from the west (Highway 169).
- Middle School (on Texas Avenue)
- Access to Texas Avenue (north of Cedar Lake Road) and the SLP Middle School is by using Louisiana Avenue, Wayzata Boulevard (frontage road) and Texas Avenue. Please see the SLP Middle School access map.
Upcoming work
Middle Stage (Stanlen Rd to Virginia Cir) and East Stage (Virginia Cir to Rhode Island Ave)
- The paving of the final layer of bituminous pavement was completed on Tuesday, November 12.
- The installation of sod was completed this week.
- The installation of the street light poles is ongoing this week.
- The streets lights to be operational by the end of next week.
- The installation of all the permanent signs and pavement markings to be completed by the end of next week.
- The signal system at Texas Avenue to be completed by the end of this week.
- Contractor will continue to clean up the site and remove equipment/materials over the next two weeks.
Project details
2024 Cedar Lake Road plans - 100%
- Cedar Lake Road Improvements (Highway 169 to Rhode Island Avenue) - geometrical layout
- Cedar Lake Road West - watermain replacement
Survey
- Survey crew in area letter – Oct. 7, 2021
Open House #1
- Open House #1 letter - Feb. 7, 2022
- Open House #1 Feb. 23 meeting - recording
- Open House #1 Feb. 24 meeting - recording
Design Development and Refinement – Spring/Summer 2022
In the spring and summer of 2022, we were out in the community asking you about existing challenges and needs for these two corridors to help inform the development of the initial design concepts to be presented at the upcoming September 2022 open houses. Here’s a summary of what we’ve been up to:
- Engaged community members at four pop-ups/community events.
- Met with stakeholders along the corridor, including Metro Transit, Park Spanish Immersion School District, St. Louis Park Fire Department, Minnesota Department of Transportation, private utility companies, and individual property owners.
- Received 550+ comments to date through our interactive map, survey, and email/phone.
Open House #2
- Open House #2 postcard
- Presentation
- Open House #2 Sept. 21 meeting - recording
- Cedar Lake Road and Louisiana Avenue Improvement design options under consideration
- Cedar Lake Road
- Alternative 1 - Multi-use trail
- Alternative 2 - Cycle tracks
- Alternative 3 - Buffered bike lanes
- Louisiana Avenue
- Alternative 1 - Multi-use trail
- Alternative 2 - Cycle tracks
- Alternative 3 - Alternative route
Open House #3
- Open House #3 postcard
- Cedar Lake Road and Louisiana Avenue preferred alternative summary
- Cedar Lake Road preferred alternative
- Louisiana Avenue preferred alternative
- Open House #3 Dec. 13 virtual meeting - recording
Public Hearing
30% design plans - approved by city council on Feb. 6, 2023
- Cedar Lake Road approved design
- Louisiana Avenue approved design
Section 4(f) De Minimis Public Comment Period
Open House #4
- Open House #4 invitation letter
- 90% design plans geometrical layout
- Open house #4 Dec. 4 virtual meeting - recording
- Cedar Lake Road and Louisiana Avenue Improvement project scope overview
- Cedar Lake Road West - watermain replacement
Section 4(f) De Minimis Impacts to Willow Park: Public Comment Period
Construction communication
Minnesota Department of Transportation (MnDOT) will be reconstructing I-394 at Louisiana Avenue in 2025. For more information, please visit the project information webpage.
The new roundabout at the intersection of Cedar Lake Road and Louisiana Avenue will not be constructed until 2026, but we have many roundabouts currently operating in our city.
Learn more about modern roundabouts and tips for safely navigating them by viewing the videos below.
For more resources on roundabouts, their features and navigation tips, visit Roundabouts in Minnesota - MnDOT (state.mn.us).